1 Construction of 42” OD X 1000 Psig Gas Transmission Pipeline from North Halisahar to Uttar Salimpur Pig Receiver Station approx. 7.20 Km under Anowara – Fouzdarhat Gas Transmission Pipeline Project (a Project of GTCL.), as JV Partner. 1000 PSIG 2018 Gas Transmission Company Limited. (GTCL)
2 Design-build, Supply, Erection, Installation, Testing & Commissioning of 85 MMSCFD Capacity Skid Mounted Gas Regulated & Metering Station for Supplying Natural Gas to Bibiyana South 400 MW CCPP at Nabiganj Upazila, Habiganj District on Turn Key Basis. under Forain S.r.l., Italy and Sunnex Ltd. 85 MMSCFD 2017-2018 Bangladesh Power Development Board (BPDB)

3

Design-build, Supply, Erection, Installation, Testing & Commissioning of 85 MMSCFD Capacity Skid Mounted Gas Regulated & Metering Station for Supplying Natural Gas to Bibiyana South 400 MW CCPP at Nabiganj Upazila, Habiganj District on Turn Key Basis. Valvitalia S.p.A System Division, Italy and Sunnex Ltd. 85 MMSCFD 2017-2018 Bangladesh Power Development Board (BPDB)

4

Sub Head Gas Connection of Multistoried Residential Building at Motijheel Govt. Colony, Dhaka - 2018 Public Works Department (PWD)

5

Installation of Filter Separators in the internal gas pipeline for Haripur Power Limited - 2017 Forain S.r.l, Italy.
6

Fabrication, Installation, Testing & Commissioning of 80 MMSCFD Capacity Skid Mounted Gas Regulating & Metering Station for Supplying Gas to NWPGCL BHERAMARA 360MW CCPP Project, under Valvitalia S.p.A System Division, Italy and Sunnex Ltd.

80 MMSCFD 2016-2017 North – West Power Generation Company Limited
7

Construction of 20" OD X 1 km X 350 psig North – West Power Generation Company Limited Interconnection Pipeline Between Bheramara CGS & Bheramara RMS.

350 PSIG 2016 North – West Power Generation Company Limited
8 Construction of 20" OD X 3.3 km X 1000 psig Gas Transmission pipeline from Titas gas fields Well # 23-24 (Sorail) to Khathihata & Well    # 25-26 (Malihata) to Khatihata of Brahmonbaria District. 1000 PSIG 2016-2017 GAS Transmission Company Ltd. (GTCL)
9

Design-build, Supply, Installation, Testing & Commissioning of 70 MMSCFD Capacity Skid Mounted Gas Regulating & Metering Station of Shahjalal Fertilizer Project, Under ValveItalia S.p.A System Division, Italy and Sunnex Ltd.

70 MMSCFD  2016-2017  Shahjalal Fertilizer Project of BCIC.
10

Installation of Magnesium Anode for Corrosion Control of Maheshkhali-Anowara (30" OD, 91 Km Long) Gas Transmission Pipeline as Temporary Basis.

1100 PSIG  2016  Gas Transmission Company Limited. (GTCL)

11

Construction of 30'' OD X 1100 psig Gas Transmission Pipeline from CTMS adjacent to Dhalghatpara Primary School to Wast Bank of Koheli River (approximately 17.2 Km) Under Maheshkhali- Anowara Gas Transmission Pipeline Project, Section-B.

1100 PSIG

2016

Gas Transmission Company Limited. (GTCL)

12

Gas Heater Maintenance work at Ashugonj Power Plant Metering and Regulating station.

 

2016

Bakhrabad Gas Distribution Company Limited (BGDCL)

13

Process Plant Up gradation work at LPG Plant, Mongla.   2016 Petredec Elpiji Ltd.

14

Design-build, Supply, Installation, Testing & Commissioning of 45 MMSCFD Capacity Skid Mounted Gas Regulating & Metering Station for Supplying Gas to Shahjalal Fertilizer Project, Fenchuganj, Sylhet on Turn-Key Basis under BCIC.

45 MMSCFD

2014-2015

Shahjalal Fertilizer Project of BCIC

15

Installation of Permanent Cathodic Protection system for 137km long 36” OD Bibiyana – Dhanua Gas Transmission Pipeline.

1000 PSIG

2014-2015

Gas Transmission Company Limited. (GTCL)

16

Bibiyana Mechanical Expansion Project, Bibiyana Gas Plant, Karimpur, Nobigonj. (JV with The Pipeline Engineers & Associates Limited.)

Max. 1250 PSIG

2013-2015

Foster Wheeler & Chevron Bangladesh

17

Mechanical, Piping and Insulation Work for Ashuganj Compressor Station Project. (JV with The Pipeline Engineers & Associates Limited.)

 

2012-2014

Hyundai Engineering Co. Ltd.

18

36” OD River Crossing Lot-1 & Lot-2 (Total 14 Nos, River) of Bibiyana – Dhanua Pipeline Project. (JV with The Pipeline Engineers & Associates Limited.)

1000 PSIG

2013-2014

EPC Contractor: MEARS Group, Inc.

Owner: Gas Transmission Company Limited. (GTCL)

19

Construction of 36” OD natural Gas Transmission Pipeline (Section-C, 32 Km.) of Bibiyana - Dhanua Gas Transmission Pipeline from West Bank of Dhanua to Atakti Road (Pakundia). (JV with The Pipeline Engineers & Associates Ltd and The Royal Utilisation Services (Pvt.) Ltd.)

1000 PSIG

2012-2013

Gas Transmission Company Limited. (GTCL)

20

Construction of 6” OD X 500 Psig X 14 Km. pipeline from Sreemongol TBS to Bhairabgonj Bazar and Construction of 6” OD Pipeline from Bhairabgonj Bazar DRS to Moulavibazar DRS and Moulavibazar.

500 PSIG

2012-2013

Jalalabad gas Transmission & Distribution System Ltd.

21

HFO Pipeline for Sirajgonj 185 MW Power Plant.

 

2012-2013

Sirajgonj 185 MW Power Plant

22

Installation of Permanent Cathodic Protection System for 163 Km Long X 20” OD Bheramara- Khulna Gas Transmission Pipeline.

1000 PSIG

2012-2013

Gas Transmission Company Limited. (GTCL)

23

River Water Intake Pipeline at Shahjalal Fertilizer Project (SFP)

 

2012-2013

China National Complete Plant Import & Export Corporation Limited (COMPLANT)

24

Construction of Fuel Hydrant system in 8 Bays Zet A1 Fuel for Air craft refueling at ShahAmanat International Airport under ENCON Engg. Ltd., South Africa.

300 PSIG

2012-2013

Shah Amanat International Airport

25

Muchai Gas Compression Project (MGCP). (JV with The Pipeline Engineers & Associates Ltd and The Royal Utilisation Services (Pvt.) Ltd.)

 

2011-2012

Chevron Bangladesh.

26

Fabrication & Erection of Gas fuel Power Plant at Ashugonj. (JV with Sigma Construction)

50 MW

2011-2012

Midland Power Plant

27

Fabrication & Erection of Crude oil Refinery Project. (JV with Sigma Construction)

3000 Barrel / Day

2011-2012

Petromax Refinery Ltd.

28

Installation, Supply, and commissioning of Cathodic Protection system for Sirajgonj, Ullapara, Shahjadpur, Bogra, Pabna and Iswardi Town gas distribution network. Length of pipeline 187 km.

60 PSIG

2011-2012

Pashchimanchal Gas Company Limited. (PGCL)

29

Construction of 20” DN X 1000 PSIG X 25 KM Natural Gas Transmission Pipeline from Monohordi to Narsingdi Valve Station # 12. (JV with The Pipeline Engineers and Associates Ltd. And  The Royal Utilisation Services (Pvt.) Limited)

1000 PSIG

2011-2012

Titas Gas T & D Company Limited

30

Operation, Maintenance and Development works of the CP System of GTCL Operated Pipeline.

500 ~ 1150 PSIG

2009-2013

Gas Transmission Company Limited. (GTCL)

31

Installation & Commissioning of Permanent Cathodic Protection system for 30” OD X 82 Km. X 1000 Psig high pressure gas Transmission pipeline from Hatikumrul (Sirajgonj) to Bheramara (Kushtia).

1000 PSIG

2011-2012

Gas Transmission Company Limited. (GTCL)

32

Construction of 10” OD X 27.29 Km. X 960 psig cross country pipeline from Nazirhat Railway station to Ring Main at Nasirabad, Chittagong.

960 PSIG

2011-2012

Karnaphuli Gas Distribution Company Limited.

33

Construction of Interconnection pipeline between Saldha-BKB pipeline and BKB-Chittagong pipeline within Bakhrabad Gas Field location including Hot tie-in.

1000 PSIG

2011-2012

Gas Transmission Company Limited. (GTCL)

34

MB-A Drilling Pad Development including Construction & Bridge Strengthening Work at Nurjahan Tea Estate, Kamalgonj, Moulavibazar. (JV with The Pipeline Engineers & Associates Ltd and The Royal Utilisation Services (Pvt.) Ltd.)

 

2011

Chevron Bangladesh.

35

Construction of 20” X 1200 meter pipe string for HDD River crossing including local logistic support at Karnafully River, Chittagong.

100 PSIG

2010-2011

Bakhrabad Gas Company. HDD Contractor: MarshingHdn.,Bgd, Malayasia.

36

Fabrication & Erection of HFO Power Plant at Faridpur. (JV with Sigma Construction)

50 MW

2010-2011

BPDB / Energy Pac

37

Fabrication & Erection of various Piping spools and Tie-in works for Process upgrade of Jalalabad Gas Process Plant. (JV with The Pipeline Engineers & Associates Ltd and The Royal Utilisation Services (Pvt.) Ltd.)

 

2010

Chevron Bangladesh.

38

Fabrication & Erection of various Piping spools and Tie-in works for Process upgrade of BIBYANA Gas Process Plant. (JV with The Pipeline Engineers & Associates Ltd and The Royal Utilisation Services (Pvt.) Ltd.)

 

2010

Chevron Bangladesh.

39

Construction of 18.00 Km long 762mm (30”) OD X 1000 PSIG High Pressure Natural Gas Transmission Pipeline from Bonpara, Natore to Mazgaon (GK Canal), Natore. (JV with The Pipeline Engineers & Associates Ltd and The Royal Utilisation Services (Pvt.) Ltd.)

1000 PSIG

2009-2010

Gas Transmission Company Limited. (GTCL)

40

Construction of 16" DN X 300 PSIG X 10.44 Km Gas Pipeline from Dighibarabo CGS to Bhulta TBS and 12" DN X 140 PSIG X 11.28 Km Gas Pipeline from Bhulta TBS to Kanchan DRS and Bhulta TBS to Araihazar.

300 & 140 PSIG

2008-2009

Titas Gas T & D Company Limited

41

Engineering, Procurement, Construction & Commissioning of 16.0 MMSCFD capacities Gas Regulating & Metering station under JGT&DSL on Turnkey basis.

1150 PSIG

2008-2009

Barakatullah Electro Dynamics Ltd.

42

Construction of 14.0 km long, 8” OD Gas Transmission Pipeline from Haripur gas field to Khadim DRS under SCCPP & SFF Project.

1000 PSIG

2007-2008

Jalalabad gas Transmission & Distribution System Ltd.

43

Supply of gas pipeline, Isolation, valves, Insulating Joints, & accessories & Installation of all equipment for Inter connection between existing 90MW CCPP unit-1 and gas turbine unit of proposed 90 MW CCPP unit-2 and Gas booster.

350 PSIG

2007-2008

Bangladesh Power Development Board (BPDB)

44

Construction of 16” DN X 140 PSIG X 19.20 Km Natural Gas Pipeline under Dhaka Clean Fuel Project.

140 PSIG

2006-2007

Titas Gas T & D Company Limited

45

Engineering, Procurement & Construction (EPC) of Cathodic Protection (CP) system of Nolka –Bogra High Pressure Gas Transmission Pipeline.

1000 PSIG

2006-2007

Gas Transmission Company Limited. (GTCL)

46

Repairing, maintenance & re-instatement of Regeneration heater of Location-1 at Bahubal, Habogonj.

2500 PSIG

2005-2006

Sylhet Gas Field Ltd.

47

Hook up work 12” dia. Titas gas field pipeline from Location-3 to Khathihata GTCL Gas Manifold station at Titas Gas Field Location-5.

1000 PSIG

2005-2006

Gas Transmission Company Limited. (GTCL)

48

Making 5600 Nos. of 75lb “A” / “R” Rail Joint by AluminoThermit Process at Tongi – Bhairab section of Bangladesh Railway.

Rail Track

2005-2006

Bangladesh Railway

49

Construction, Testing & Commissioning of Bogra Town DRS.

1000 PSIG, 8.0 MMSCFD

2005-2006

Pashchimanchal Gas Company Limited. (PGCL)

50

Construction of 37 km. long 20” OD Gas Transmission pipeline from Chandaikona (MLV-1) to Bogra. (JV with The Pipeline Engineers & Associates Ltd and The Royal Utilisation Services (Pvt.) Ltd.)

1000 PSIG

2004-2005

Gas Transmission Company Limited. (GTCL)

51

Installation of Cathodic Protection System at Shathia, Bera, Shahjadpur, Pabna&Iswardi Gas distribution network. Total Length 255 Km.

60 PSIG

2004-2005

Pashchimanchal Gas Company Limited. (PGCL)

52

Construction of 8”, 6", 4", 3", 2" DN Network Balancing Natural Gas Pipeline at Purana Paltan, Fakirerpul, Santinagar, Dhaka and adjacent Area.

60 PSIG

2003-2004

Titas Gas T & D Company Limited

53

Construction of 16” DN X 300 PSIG X 5.5 Km Natural Gas Pipeline from Demra CGS to Dhania TBS. (JV with The Royal Utilisation Services (Pvt.) Ltd.)

300 PSIG

2002-2003

Titas Gas T & D Company Limited

54

Construction of 4", 3", 2", 1" DN Network Balancing Natural Gas Pipeline at Keranigonj, Zinziria, Suvaydda and it's adjacent Area.

 

2001-2002

Titas Gas T & D Company Limited

55

Construction of 4” DN X 1000 PSIG X 11.26 Km pipeline including a Metering and Regulating (MNR) station on Turnkey (Design, Procurement, Construction and Commissioning with Telecom system at Ghatail Cantonment, Tangail.

1000 PSIG

2000-2001

Titas Gas T & D Company Limited

56

Construction of 500 meter section gas Transmission Pipeline of JGTDSL including hydrostatic testing and removal of 1800 meter 6” DN High Pressure Gas pipeline at MB-1 (Magurchara, Moulavibazar)

1000 PSIG

1999-2000

Occidental of Bangladesh Limited.

57

Fabrication, Installation and Commissioning works of a Regulating & Metering Station including relevant pipeline (20" DN X 1000 PSIG) and civil Construction works at Beanibazar in a view to supply gas at Beanibazar town distribution network.

25.0 MMSCFD &

1000 PSIG

1999-2000

Jalalabad gas Transmission & Distribution System Ltd.

58

Construction of 12” DN X 140 PSIG X 8.59 Km. Gas Pipeline from Godnail DRS to Kadamtali DRS at Narayangonj.

140 PSIG

1999-2000

Titas Gas T & D Company Limited

59

Construction of 6” dia. Gas Gathering pipeline at Rashidpur Gas Field. Length 18.11 Km.

3000 PSIG

1998-1999

China Huanqui Chemical Engineering Corporation.

60

Temporary 3” dia. interconeection with Jamuna Bridge crossing of GTCL.

140 PSIG

1997-1998

Pashchimanchal Gas Company Limited. (PGCL)

61

Construction of 8” dia. Cross country pipeline from kuchai, Sylhet to Madanpur towards Chatak. Length 19.25 Km.

1000 PSIG

1997-1998

Jalalabad gas Transmission & Distribution System Ltd.

62

Construction of 10” dia. Gas feeder line at 90MW Power station, Fenchugonj, Sylhet. Length 0.460 M.

1000 PSIG

1996-1997

Jalalabad gas Transmission & Distribution System Ltd.

63

Construction of 10” dia. cross country pipeline from Hetimgonj to Khadim DRS including a 60 meter wide river crossing. Length 10.92 Km.

1000 PSIG

1996-1997

Jalalabad gas Transmission & Distribution System Ltd.

64

Construction of 3” dia. Cross country pipeline from Kapnapahar to Raj-kee tea Garden. Length 20.796 Km.

1000 PSIG

1994-1995

Jalalabad gas Transmission & Distribution System Ltd.

65

Construction of 6” dia. Feeder line at 90MW Power station Fenchugonj, Sylhet. Length 0.514 M.

1000 PSIG

1994-1995

Jalalabad gas Transmission & Distribution System Ltd.

66

Construction of 1” – 4” dia. Low pressure gas distribution pipeline at Purbabag, Bhadeswar. Length 4.50 Km.

60 PSIG

1994-1995

Jalalabad gas Transmission & Distribution System Ltd.

67

Construction of 1” – 4” dia. Kulaura town gas distribution networks. Length 21.80 Km.

60 PSIG

1994-1995

Jalalabad gas Transmission & Distribution System Ltd.

68

Construction of 1” – 4” dia. low-pressure gas pipeline in Golapgonj Area, Sylhet. Length 8.579 Km.

60 PSIG

1994-1995

Jalalabad gas Transmission & Distribution System Ltd.

69

Construction of 1” – 4” low-Pressure pipeline at Perozpur, Sylhet. Length 24.63 Km.

150 PSIG

1993-1994

Jalalabad gas Transmission & Distribution System Ltd.

70

Construction of 1” – 4” low pressure pipeline and installation of risers with in Sylhet Zone. Length 17.00 Km.

65 PSIG

1993-1994

Jalalabad gas Transmission & Distribution System Ltd.

71

Construction of 1” – 2” low pressure pipeline and installation of risers with in Sreemongol Zone. Length 9.948 Km.

100 PSIG

1993-1994

Jalalabad gas Transmission & Distribution System Ltd.

72

Construction of 1” – 2” low pressure pipeline and installation of risers with in Sylhet Zone. Length 18.71 Km.

100 PSIG

1993-1994

Jalalabad gas Transmission & Distribution System Ltd.

73

Construction of 1” – 2” Town distribution network in Sylhet town. Length 12.72 Km.

100 PSIG

1993-1994

Jalalabad gas Transmission & Distribution System Ltd.

 

TECHNIC OTHER MISCELLANEOUS WORKS ACHIEVEMENT

SL. NO.

WORK DESCRIPTION

YEAR

CLIENT

1

Welding of 4,500 Nos. of Meter gauge rail joints by AluminoThermit process in Dhaka-Chittagong Section. Length 42 Km.

2001-2003

Bangladesh Railway

2

Welding of 5,600 Nos. of Meter gauge rail joints by AluminoThermit process in Tongi-Bhairab Section. Length 50 Km.

2001-2003

Bangladesh Railway

3

7000 Nos. of 75lb. “A” Rail joint welding by AluminoThermit in Tongi-Mymensingh Section.

2000-2001

Bangladesh Railway

4

Welding of 30” OD Casing pipe (Conductor welding) at Barsala yard

1999-2000

Occidental of Bangladesh Limited

5

Providing Welders, Fitters and Supply of Welding machinery on Rental Basis.

1999-2000

Occidental of Bangladesh Limited

6

3 Nos. 20” OD Connector’s welding at casing of JB#1

1997-1998

Occidental of Bangladesh Limited

7

Construction, Fabrication & supply of Engine service platform for Lackatora Gas plant of UNOCAL Bangladesh Ltd.

1997-1998

Kvaerner Process system Asia Pacific Sdn. Bhd.

8

Fabrication & Installation of  Platform & ladder at Lackatoora Gas Plant of UNOCAL Bangladesh Ltd.

1997-1998

Kvaerner Process system Asia Pacific Sdn. Bhd.

9

Construction, fabrication & supply of 2500 gallon portable water tank for Lachatoora gas Plant

1997-1998

Kvaerner Process system Asia Pacific Sdn. Bhd.

10

Construction, fabrication & supply of 500 gallon portable Diesel  tank.

1997-1998

Kvaerner Process system Asia Pacific Sdn. Bhd.

11

Construction of CI Shed over Caravans at Lachatoora field camp, 82sq. M.

1996-1997

Deautag Bangladesh Branch.

Our Services

Hotline: 01844-143001

Address
Road No#02, House No#221,

Baridhara DOHS,Dhaka-1206, 
Bangladesh

Phone: +880-2-841-2871

Fax: +880-2-841-1564
Email: info@technic.com.bd
Web: www.technic.com.bd